Interconnection / Net Metering - Process & Checklist for Installers 

Phase I:  

Phase II:  

  • LPEA Engineering reviews Interconnect/Net Metering Application 
    • Interconnect request approved or 
    • Certain requirements must be completed prior to obtaining approval for interconnection. 
  • LPEA performs Pre-Inspection  

Phase III: 

  • Installation Process 
    • Construction of array 
      • Review LPEA’s Interconnection Standards prior to installation  
      • Production Meter Socket (If required, please email renewables@lpea.coop one week in advance to coordinate pick up).
      • Accessible Disconnect 
    • State Electrical Inspection  

Phase IV: 

Phase V: 

  • LPEA performs Final Interconnect Inspection within two weeks of receiving Phase IV documents 
    • Installers may be required to be present at final inspection  
    • LPEA will schedule a meter change for Net Metering (if required)