Interconnection Process & Checklist for Installers
Step 1: Submit an Interconnection Application
Required documents for application submittal:
- Interconnection Request Form
- One Line Diagram of RG System
- Accessible AC disconnect
- Production meter socket if AC capacity is greater than or equal to 50 kW
- Site Plan of RG System
- Load Data Sheet for New Construction
* The member must have an account number prior to submitting an application.
Step 2: LPEA Engineering Review (2-4 weeks)
LPEA Renewables and Engineering teams review Interconnection Application for completeness and for compliance with requirements.
- Interconnection request approved
OR
- Certain requirements must be completed prior to obtaining approval for interconnection.
- Starting July 1, 2024: The Interconnection Agreement must be signed and returned to renewables@lpea.coop to interconnect and become a net-metered account. LPEA will countersign the Interconnection Agreement and email it to the member.
Note: LPEA Engineering approval valid for 12 months. Projects must be placed in service within 12 months or a new application will be required.
Step 3: Installation Process
- Construction of system
- Review LPEA’s Interconnection Standards prior to installation
- Accessible AC disconnect
- Production meter (*If applicable please email renewables@lpea.coop one week in advance to coordinate meter pick up. Meter socket provided by installer.)
- State Electrical Inspection
*The design and installation of a PV solar system may require approval from one or more of the following: Fire Protection District, County, or Municipality. The need for approval may depend on the location of the PV solar system, what type of building it is situated on, or if it is a ground-mounted system. Please reach out to the applicable authority prior to development.
Step 4: Submit Completion Documents
**IMPORTANT: Systems may NOT be energized until final completion documents are received and LPEA grants permission to operate.
Email the below documents to renewables@lpea.coop:
- Approved State Electrical Inspection Final Report
- Proof of LPEA’s Required Inverter Settings
Step 5: LPEA Final Inspection
LPEA performs Final Inspection within two weeks of receiving final completion documents from step four.
- Installers may be required to be present at final inspection.
- "Permission to Operate" certificate will be issued upon LPEA approval.